Goldman Sachs estimates that the power supply capacity and electricity demand of data centers in the United States have both increased by nearly 30% since this year, contributing to more than one-third of the overall increase in electricity demand across the country. The firm predicts that there could be an additional 52 gigawatts of data center power supply capacity put into operation by 2028, and based on this, it is bullish on natural gas prices at Henry Port from 2028 to 2030.
After signing the lease for the data center premises, there is still a need to wait for the power infrastructure to be in place. Applied Digital announced this week that it will rent out 150 megawatts of critical IT capacity, with delivery expected to begin in the first half of 2028. The specific timeline depends on project development, utility power supply arrangements, and regulatory approvals.
The scale of supporting infrastructure construction in Louisiana is even larger. The utility company Entergy is building a 7.5 gigawatt gas power generation project for the Meta data center. According to the schedule compiled by Rabobank, the first units are planned to be put into operation by the end of 2028, with the remaining units to be constructed in batches until 2031.
The agreement signed between Entergy Louisiana and Energy Transfer plans to provide the first batch of natural gas transmission services starting from February 2028, with an initial capacity of 25 trillion British thermal units per day.
Data center developers are also considering providing their own power sources. Morgan Stanley pointed out this week that rising residential electricity costs and increased attention to grid capacity may prompt developers to purchase equipment and build on-site power generation facilities themselves. However, gas-powered equipment is still subject to limitations regarding emissions, noise, and land occupation.
It is estimated that stricter approval requirements may result in a delay of the delivery of the data center IT in the United States, with a capacity of approximately 5 gigawatts, originally scheduled for 2028, to 2029.
New Mexico’s Project Jupiter project plans to use natural gas fuel cells for power generation. According to Bloomberg, the Green Chile pipeline that supplies gas to the project had to be rerouted due to obstacles on the original route, and the target date for commissioning has been postponed to February 2027. Morgan Stanley expects that the project may obtain air emission permits and final pipeline approval in early 2027.
The expansion of natural gas pipelines also requires a relatively long period of time. According to Bloomberg, JPMorgan has decided to invest $4.2 billion in building the Permian Link pipeline, which will transport natural gas from the Permian Basin to northern Texas to supply gas to users such as data center clusters. The pipeline is designed to have a capacity of 2.8 billion cubic feet per day and is scheduled to be put into operation by the end of 2030.
Liquefied natural gas exports have led to a more direct demand for raw material gas. A report recently released by JPMorgan Chase indicates that from November until the time of the report, the average daily flow of raw material gas at liquefied natural gas facilities in the United States reached 20.9 billion cubic feet, higher than the 18.8 billion cubic feet in the same period last year. Among them, the average daily flow of raw material gas at the Golden Pass terminal reached 690 million cubic feet, a significant increase from 350 million cubic feet in the third quarter of this year.